Innovative Technology Used at Construction of Cable Lines in Skolkovo

Innovative technology was used in the construction of the cable lines in Skolkovo, novostienergetiki.ru report. According to the press-service of FGC UES, the Main Power Grids of Center, which are the part of the company completed the check-out of the cable power transmission lines 220-500 KW in the innovation center of Skolkovo, which is being built in the Greater Moscow Area.
As novostienergetiki.ru report with the reference to the press-release by FGC UES, the check-out of the innovation power transmission lines was carried out with the use of the newest movable high-voltage resonant-type machine WRV 74/180Т, which enables checking the cables 110 KW up to 12km of length in the field, the cables 220KW up to 9 km of length, and the cables 500 KW up to 3.5 km of length. At present this is the first and so far – the only machine of this kind in the Russian Federation.
The works, which have been carried out, as the press-release says, will allow avoiding serious short circuits and will improve the stability of the cable lines operation considerably after they are commissioned. Novostienergetiki.ru remind of the fact that the high-voltage check-out of the cable power transmission lines is a very important stage in their construction.

Метки: , ,

Интересная статья? Поделитесь ей с друзьями:

Вы должны выполнить вход/регистрацию чтобы комментировать Войти

Также Вы можете войти используя: Yandex Google Вконтакте Mail.ru Twitter

Новость дня

© 2024 «Новости энеретики»
г. Москва
Тел.: (495) 540-52-76
Карта сайта

Перепечатка материала с сайта без разрешения Редакции запрещена. За содержание новостей, объявлений и комментариев, размещенных пользователями сайта, редакция журнала ответственности не несет. Вся информация носит справочный характер и не является публичной офертой.

Яндекс.Метрика Яндекс цитирования