Ust-Labinskiye power grids embarked on the complex capital repairs of the substation 110 kv Korenovskaya-Tsentralnaya, with the total power capacity of 50 Megavoltmaperes. The expenditure on the repairs is to comprise over three million rubles.
During the summer months OAO Kubanenergo is to execute over 60 maintenance activities at the main and the auxiliary substation equipment.
The engineers are going to pay special attention to the repairs of the transformers T1 and T2 with the voltage 110 kv, circuit breakers, disconnecting switches, short-circuiters, built in sections of buses of different voltage types, as well as cubicle switchboards, which are aimed for receiving and distributing electrical energy of the alternate three-phase current, equipment of relay protection and control, teleautomatics.
Commissioned in 1970, Korenovskaya-Tsentralnaya substation is still one of the largest substation of the Korenovskiy district. It is responsible for the uninterrupted power supply of 25 population centers and almost 70 important social objects of the regions including the large industrial processing enterprises – Korenovskiy sugar plant and the dairy and canning plant.
Метки: power grid companies, repir campaign, substation, Кубаньэнерго
Интересная статья? Поделитесь ей с друзьями: