This is done during the capital overhaul of the substation, or summing up the results of tests in cases where they show deviations from the regulations. In general, transformers are replaced, because they are the main link in the scheme of power supply to consumers.
Since the beginning of the year about two dozen power plants were replaced at the Perm transformer substations in the districts of Yanvarskiy, the Tsentralniy, the Bunkombinat, Vladimirskiy, Yuzhny. Parkoviy, Zaozerye. Those that have a low insulation resistance, poor performance of transformer oil were replaced with modern, virtually maintenance free or good quality ones, which have recently been repaired.
On average, each year the power engineers in the regional center energy perform the capital repairs of 85 — 95 transformer substations and distribution points. This year their number will be increased to 97 units, which would cost the branch of JSC «IDGC of Urals» — «Permenergo» 5.65 million rubles.
The company intends to continue its actively work within the framework electricity supply stability program of the capital of the Perm Territory.
Метки: capital repairs, power transwormer, transformer substation, Пермэнерго
Интересная статья? Поделитесь ей с друзьями: