October 28 saw the turbine generators #8 and # 7 of the fourth power generating unit at the Leningradskaya nuclear power plant connected to the grid at 11.51 and 20.05 respectively after replacing the transformer at one of the phases. On October 29 at 111.20 the unit load was restored to nominal.
The power generating unit was set in operation in accordance with the requirements of safety operation process regulations. As of October 31 power generation units # 2,3 and 4 are in operation. The first power generating unit is in the process of scheduled maintenance. The radiation background in the station and the adjoining territory is on the level which complies with the normal operation of power generating units and does not exceed natural background parameters.
Метки: Leningradskaya nuclear power plant, nuclear power, nuclear power industry, nuclear power plant
Интересная статья? Поделитесь ей с друзьями: