Within the framework of the execution of measures aimed at repairing grid equipment the power engineers are planning to repair 487.1 km of overhead power transmission lines with the voltage rate of 10 kv, 268.6 km of OL with the voltage of 33 kv, 16 km of OL with the voltage of 10 kv and 460.4 km of OL with the voltage of 0.4 kv.

Besides, the grid company is to carry out the capital repairs of 12 substations 110 kv and 19 substations 35 kv, to repair 3 power transformers and replace 3 accumulating batteries at the substation 110 kv. In compliance with the schedule of repair program in 2013 the energy company is to repair 249 transformer substation and 143 transformers.
Next year Vologdaenergo is planning to pay a special attention to clearing forest corridors. Vologda power engineers are planning to clear off 2829.6 ha of forest corridors along the power transmission lines routes with the voltage type of 110/3/10 kv.

Apart from the basic program the staff of Vologdaenero intend to repair administrative and production buildings, auto transport and special vehicles.

Метки: , , , , ,

Интересная статья? Поделитесь ей с друзьями:

Вы должны выполнить вход/регистрацию чтобы комментировать Войти

Также Вы можете войти используя: Yandex Google Вконтакте Mail.ru Twitter

Новость дня

© 2024 «Новости энеретики»
г. Москва
Тел.: (495) 540-52-76
Карта сайта

Перепечатка материала с сайта без разрешения Редакции запрещена. За содержание новостей, объявлений и комментариев, размещенных пользователями сайта, редакция журнала ответственности не несет. Вся информация носит справочный характер и не является публичной офертой.

Яндекс.Метрика Яндекс цитирования