A high alert regime was introduced in the power utilities of Sochi in order to provide the Olympic objects with electricity and to ensure timely response to emergency situations. The emergency response center, which is personally headed by Oleg Budargin, the head of FGC UES (Federal Grid Company of the Unified Energy System) is controlling […]
After capital repairs 72 overhead lines 35-110 kV with the total length of almost 370 km, in which 254 transmission towers and 55 km of wires have been replaced. Over 1000 km of overhead lines 0.4-10 kV have been repaired, 14 transmission towers have been installed, 1.2 thousand km of wires have been replaced. Complex […]
Over 8 thousand km of overhead power lines of different voltage classes, 44 substations with the voltage of 35-110 kV and 2200 transformer substations 6-10/0.4 kV have been repaired over the 10 months of 2012. One of the priority fields in the activities of power engineers this year is the capital repairs of overhead power […]
Besides, within the framework of the execution of the repair program-2012 OAO Kubanenergo conducted complex maintenance of 86 substations 35-110 kV, 665 transformer substations 10/0.4 kV. In the course of the repair works in the Krasnodar region and the Republic of Adygei the engineers of OAO Kubanenergo replaced 3 574 outdated, worn-out transmission towers with […]
The problem of birds (especially rare species) dying of electroshock is a matter of special concern on the part of environmentalists and power engineers. Birds are electrocuted while landing on overhead power transmission lines to rest. Touching the conducting parts of electric installations they cause short circuits and failures, which result in power outages with […]
The power line Korenovskaya-Burakovskaya has been in operation since 1964 and is the main power source for the 26 transformer substations 10-0.4 kv and four overhead power transmission lines 10 kv, which supply electricity for the population center of Burakovskiy in the Rohenovskiy district of the Krasnodar Territory. In case the technological failures in the […]
On September 4 at 10:20 a.m. as a result of the works on tree cutting along the motor road from the village of Parkovy to the village of Zeleny, which were carried out by some outsiders without compliance with OAO Kubanenergo, a poplar tree fell on the power transmission line 10 kV. The subsequent breach […]
Evening of August 7 saw the thunderhead over the territory of the Novgorod region, accompanied by strong gusts of wind and heavy rainfall. In some areas of the region power supply to consumers of the branch of IDGC of North-West «Novgorodenergo was interrupted.» Already within an hour the engineers were able to connect more than […]
The officers of the Police Department of the Adler district of Sochi with the security officers and the employees of the service of electrical transmission lines of the Sochi Electrical Grids – the branch of «Kubanenergo» — detained the suspects in the theft of copper wire from high voltage overhead lines. From March to July, […]
The new substation will be equipped with the new transformers with the capacity of 40 MVa each. At present the power engineers are embarking on their assembling at the prepared subconstructions. The construction of the substation 110/35/6kv Pal’nyki is presupposed by the cooperation agreement between the government of the Perm Territory and OAO IDGC of […]