During the first six months of 2012 the cost of the repair campaign of JSC «IDGC of North-West» «Vologdaenergo» amounted 128.3 million rubles.
Compared to the same period last year, the company increased the cost of the repairs by 16%.
During the first half-year period 125.5 km of transmission lines 110 kV were repaired, as well as 50.8 km of overhead lines of 35 kV and 843.8 km on the lines of 0.4-10 kV. In addition, during the repair work on power branch «Vologdaenergo» 2652 transmission towers and 362.6 km of wire were replaced.
As a part of the repair program in the grid company the complex repairs of the two 110 kV substations and 35 kV substation one were carried out, as well as the repairs of the disconnector switches, 55 of which are in the 35-110 kV substations. Besides, the power grid company has cleared 753.57 ha of the forrest corridor along the lines of power transmission lines of all voltage classes.
Most of the work was done using the company’s own resources.
Метки: IDGC of North-West, power tranfromer, repair campaign, substation, transmission tower, Вологдаэнерго