By the end of 2012 it is planned to complete the reconstruction of outdoor switchgear — 110 kV, one of the biggest substation devices in the region has 31 feeders, 16 of them belong to the consumers.
«Tyumenskaya CHPP-1 has two generating units that meet the current requirements of the combined production of electricity and heat, based on the combined cycle technology. We carry out a program for improving the efficiency of existing equipment to increase the security of power supply for local consumers, and the stable operation of the station in the unified power grid «, — said Dmitry Petrikevich, the Executive Director of Fortum in the West Siberian region.
As a part of the reconstruction of the outdoor switchgear the wide-area measurement system (WAMS) is being implemented. Collecting and processing information about the processes occurring in electric networks will be carried out in real time. It is planned to use GPS to adjust the system time. The new technology of recording the parameters of transient states is designed to meet the challenges of emergency management, of the analysis of the dynamic properties of the Unified Energy System of Russia, and on the whole — to improve system reliability and to assure power supply to consumers.
The reconstruction project of the water treatment plant (WTP) on the basis of a counter ion exchange softening and demineralization has moved to the final stage. New WTP will operate in a more economical mode and will reduce the use of chemicals for treating water for technological needs of the plant and heating system by about 20 percent a year.
The maintenance campaign and the preparation of the station for the autumn-winter period are carried out in accordance with the schedule. The inspection and scheduled maintenance of gas and steam turbines, hot-water equipment unit number 1 have been completed. On the eve of the heating season the average and current repair of two boilers of high steam, which have a significant role in the preparation of the coolant and heating of Tyumen, is to be held.