A high alert regime was introduced in the power utilities of Sochi in order to provide the Olympic objects with electricity and to ensure timely response to emergency situations. The emergency response center, which is personally headed by Oleg Budargin, the head of FGC UES (Federal Grid Company of the Unified Energy System) is controlling […]
“The city is developing, it requires more capacity. After the reconstruction of the substation Solikamsk-Gorodskaya power reliable operation of power grids will be provided”, — the Mayor of the Town of Solikamsk Sergei Devyatkov says. The reconstruction of the substation 35/6 kV Solikamsk-Gorodskaya was carried out within the framework of the investment program of the […]
Over 8 thousand km of overhead power lines of different voltage classes, 44 substations with the voltage of 35-110 kV and 2200 transformer substations 6-10/0.4 kV have been repaired over the 10 months of 2012. One of the priority fields in the activities of power engineers this year is the capital repairs of overhead power […]
Besides, within the framework of the execution of the repair program-2012 OAO Kubanenergo conducted complex maintenance of 86 substations 35-110 kV, 665 transformer substations 10/0.4 kV. In the course of the repair works in the Krasnodar region and the Republic of Adygei the engineers of OAO Kubanenergo replaced 3 574 outdated, worn-out transmission towers with […]
The energy circuit, which is planned to be created at the south of Kuyzbass by the engineers of MES Siberia, will include substations Elanskaya, NKAZ-2, West-Siberian with the voltage of 220 kV and substations Kuzbasskaya, Noivokuznetskaya with the vo9ltage of 500 kV. The availability of two independent power sources for each substation will allow to […]
Over 40 houses were left without electricity in the Cossack village of Chepiginskaya in the Bryukhovetskiy district in the night of November 13. The power outage was caused by a driver of a motor vehicle VAZ 2106 colliding with the transmission tower o.4 kV. The driver of the vehicle was identified. At present the size […]
Within the framework of investment projects on the reconstruction of substations with the voltage class 100 kV in terms of replacing isolators and short circuitors with sulfur hexafluoride circuit breakers, Vologdaenergo mounts new equipment at the substation 110 kV Nifantovo in the Sheksna district of Vologda region. In the course of the reconstruction they will […]
The engineers of INTER RAU UES commissioned a combined cycle power unit PGU-450 at the Urengoyskaya SDPP, which resulted in raising the installed capacity of the power plant from 24 to 474 Mwt. The units allows to partially resolve the problem of energy deficit in the north of Tyumen region. PGU-450 combines steam and gas […]
From January to October 2012 the power plants of Krasnoyarsk energy system produced 37 billion 404.2 million kWh of electrical energy, which is by 4% less than the production volume for the 10 months of 2011. According to the current information of the branch of OAO CO UES Regional Dispatch Office of the Energy System […]
The Russian Operator exporting electrical energy in the Far East – OAO Eastern Energy Company – exported to China and Mongolia over 2 billion Kwh of electrical energy during the three quarters of 2012. For the past 9 months OAO Eastern Energy Company delivered to China 1.8 billion Kwh of electrical energy within the framework […]