The branch of JSC «IDGC of North-West» «Vologdaenergo» plans to complete the project on reconstruction of the substation 110/10 kV «Roslyatino» in the Babushkinskiy district of the Vologda region before the end of 2012. The capital investment into the project will amount to 169.4 million rubles.
During the reconstruction the contractor organization performed the work of preparing the foundations for equipment, installed the support desk set of the voltage class 110 kV and the lightning rod. Also on the site of the power object the casting of foundations for transformers was carried out.
In accordance with the project due to the reconstruction of the SS «Roslyatino» the equipment of open distribution unit (ORU) 110 kV will be replaced, the power transformers 110/10 kV are to be replaced with the two transformers with the capacity of 2.5 MVA each. In addition, the substation will have relay protection and remote control systems upgraded.
The power object – the substation 110/10 kV «Roslyatino», which provides the power supply for hospitals, schools, boiler rooms, wells, 27 settlements with a population area Babushkinsky (2647 people), businesses and agriculture, wood processing, is considered to be socially important . The project will improve the quality and reliability of electricity supply for Babushkinsky district.
Метки: electricity, IDGC of North-West, power transformer, repair works, substation, substation repair, Вологдаэнерго