After the Russian-Vietnamese negotiations came to an end, Dmitriy Medvedev, the head of the Russian Government, said that after 2013 the parties will discuss the project of creating a free trade zone. “We have discussed the prospects of mutually beneficial economic cooperation within the framework of the free trade zone, outlined the plan of necessary […]
On October 7 2012 at 20:40 the generating unit # 2 of Leningradskaya NPP was connected to the grid after completing repairs at the turbine generator # 3 within the framework of the scheduled intermediate maintenance. The start of the generating unit was carried out in accordance with the requirements of safe operation. It should […]
Rostovskaya nuclear power plant fulfilled the September plant of electricity production by 114.3%. The schedule volume being 937 million KWh, the actual production comprised over 1.70 billion KWh. As of October 1, since the beginning of the year Rostovskaya NPP has generated almost 11.158 billion KWh, since the launch – 105. 504 billion KWh. The […]
On September 25 2012 at 08:08 a.m. the generating unit # 2 of the Khmelnitskaya nuclear power plant was disconnected from the power grid of Ukraine due to the response of the turbine protection in connection with the vibration amplification. The radiation situation at the industrial estate and the adjacent regions has not changed and […]
Beloyarskaya NPP have accumulated rich experience in operating the unique progressive type of fast neutrons reactor units, which gives the opportunity to overcome the dead end of the “thermal” reactors – the limited natural deposits of uran-235. “This technology is possible at the level of a state”, — says the ranking representative of the Moscow […]
In August the Kurskaya nuclear power plant produced 2.475 billion kWh electrical energy, overfulfilling the plan by 3%. The consumers received over 2.294 billion kWh, which exceeds the planned parameter by 4.6%. The installed capacity utilization factor comprised 83.18%, while the planned parameter was 80.61%. The total amount of electrical energy produced by the Kurskaya […]
From August 31 to September 2012 the power plant is receiving a peer review from the World Association on Nuclear Organizations (WANO). There are 21 participants of the inspection from the USA, Germany, Ukraine, India, Slovakia, Bulgaria, Armenia and Russia. They are top-ranked globally recognized specialists in the nuclear power industry. The total work experience […]
On August 28 at 19:14 the turbine generator TG-14 of the generating unit № 5 of the Novovoronezhskaya nuclear power plant was restarted after the preventive maintenance and refueling. During preventive maintenance the turbine and reactor compartments of the generating unit № 5 were dissasembled and repaired, there was a checkout of the state of […]
The generating unit was stopped on July 20 as a result of switching off the turbine plant. There has been no damage of the equipment and systems of the plant, nor the violations of the limits and the safety operation terms. On July 21 2012 at 5:45 the generating unit 3 of the Kalininskaya nuclear […]
According to the contract signed in October 2011, the Kharkov-based plant Turboatom manufactured two block-module capacitors with the non-corrosive pipe system for the turbine driven feed water pump of the turbo-installation with the capacity of 500 Mw for the fifth generating unit of the Novovoronezhskaya nuclear power plant. The first capacitor was sent to the […]